1. Implementation of the test >
Static discharge generator The test plan shall be used in accordance > Direct and indirect discharge . It includes: —— a typical working conditions of the test equipment;
—— whether the test device is based on desktop or landing equipment Test;
—— Determine the applied discharge point;
-The on each point, use contact discharge or air discharge;
—— The test level used;
-The number of discharge times applied to each point in conformity test;
—— Whether the installation test is also carried out.
In order to formulate a test plan, some investigation test may be performed.
2, Test results and test reports
This standard is given > Static discharge generator
The guiding principles of the test results related to this standard and test report.Due to the diversity and differences of equipment and systems, the impact of determining testing on equipment and systems is more difficult. >
If the professional standardized technical committee or product technical specification does not give different technical requirements, the test cubs should be performed according to the test conditions and functional specifications of the test equipment The following classification:
1. The performance within the technical requirements limit is normal; 2. Can recover by itself;
3. The function or performance is temporarily reduced or lost, but the operator is required to intervene or systematically reset;
4. Device (component) or software damage or data loss causes cannot be restored to normalDecrease or lose function.
The device should not have dangerous or unsafe consequences due to the test specified in this standard.
During the acceptance test, the description of the test program and test results must be described in a special product standard.
Generally, if the device shows its anti -interference degree during the entire test, and after the test is over, the test device meets the functional requirements in technical specifications, indicating that the test is qualified.