Shanghai Qianshi analyzes the operation of the electric blast furnace

Electric wind drying oven is a common drying oven product, widely used in electromechanical, chemical, plastic, light industry and other industries, scientific research institutions to bake, dry and cure various products and samples. , heat treatment and other practical heating. How should users operate the electric wind drying oven? The following editor introduces the operation steps of the electric wind drying oven in detail and hopes to help everyone. 85eTextile Testing Instruments, Testing Equipment Manufacturer

Operation steps of electric air drying oven85eTextile Testing Instruments, Testing Equipment Manufacturer

1. Damper adjustment: According to the moisture of the drying goods, turn the damper adjustment knob to the appropriate position, generally to z position; When it is relatively humid , set the adjustment knob to the Three position (Note: the damper adjustment range is approximately 60 inches).85eTextile Testing Instruments, Testing Equipment Manufacturer

2. Sample placement: Place the Zu Place items to dry in the electric heater. Inside the dry box, there should be some clearance at the top and bottom to keep the airflow in the working space unimpeded, and close the door.85eTextile Testing Instruments, Testing Equipment Manufacturer

3. Set the desired temperature: Press the SET -Button. At this time, the PV screen will display “5P”. Use ↑ or ↓ to change the temperature value displayed on the original “SV” screen until it reaches the required value. After the setting is complete, press the SET button and the PV will display “5T” (entering the timing function). When not using the time function, press the SET button again, the PV screen will display the measured temperature and the SV screen will display the set temperature. 85eTextile Testing Instruments, Testing Equipment Manufacturer

4. Start-up: Switch on the power supply of the rapid electric drying oven and press the fan switch. At this point lethe operating indicator lights up and the engine is running. After the temperature controller displays the “Self-inspection” process, the PV screen should display the temperature measured in the working space. The SV screen should show the set temperature to be dried during use, and the drying oven will start to work at this time. 85eTextile Testing Instruments, Testing Equipment Manufacturer

5. Checking temperature control: When you first turn it on, or after prolonged use, or when there is a change of season (ambient humidity), the error between the temperature measured in the working room and the actual temperature must be checked, i.e. H. the accuracy of the temperature control. 85eTextile Testing Instruments, Testing Equipment Manufacturer

6. Timing adjustment: when you use timing, the PV screen will display “5T”, the SV screen will display “0”; use the plus button to set the required interval (minutes); the setting is When the process is complete, press Sie the SET button to put the drying box into the operating state. 85eTextile Testing Instruments, Testing Equipment Manufacturer

7. Shutdown: After drying. If you need to replace the dry items, turn off the fan switch before opening the box door to prevent the dry items from being blown away; after replacing the dry items (Note: When taking out the dry items, be careful not to burn yourself. Close the door, and then turn on the fan switch, the electric air drying box will start the drying process again. If you do not take out the items take out immediately, you should first turn the damper adjustment knob to At Z and turn off the power switch to keep the box dry.If you don't want to keep drying the laundry, set the damper to three and turn off the power switch off .After the box cools to room temperature,take it out of the box.Dry the artikel. Wipe the studio dry. 85eTextile Testing Instruments, Testing Equipment Manufacturer